Parameter Setting

This section describes how to set plant or inverter parameters.

Prerequisites

The user has the permission of the “string IV curve scan and diagnosis”.

Procedure

1.Click “Advanced -> String IV curve scan and diagnosis” to enter the corresponding interface.

2.Select the desired plant from the left plant list.

3.Click “Setting” on the operation bar to enter the “IV Intelligent curve analysis” interface. Enter the “Plant parameter setting” interface by default.

3.Perform the following operations if necessary.

  • Set PV module parameters applicable to the whole plant on the “Parameter Setting” interface. After finishing the parameter setting, click “Confirm” to save the operation.

  • Click “Unit parameter setting” and select the desired inverters. Click “Settings” on the operation bar corresponding to the selected inverter, to set parameters for the single inverter. After finishing parameter setting, click “Confirm”.

  • Optionally, click “Unit parameter setting” and select several desired inverters. Click “Batch settings” to set parameters for the several inverters. After finishing parameter setting, click “Confirm”.

  • Click the tab “PV module management”, to add, delete, or view PV module information.

    • Query PV module: enter PV module manufacturer, select module type, and enter module model. Click the icon to view corresponding PV modules.

    • Add PV modules: click “Add” to enter the corresponding interface. Fill in corresponding information and click “Confirm”.

    • View PV module information: click the icon in the operation bar to enter the corresponding interface, on which you can view detailed information on the PV modules.

    • Modify PV module information: click the icon in the operation bar to enter the corresponding interface, on which you can modify the information on the PV modules.

    • Delete PV module information: Click the icon in the operation bar, click “Confirm” on the pop-up window, and click “Confirm” on the prompt window to finish the operation.

    • Batch delete: select multiple pieces of PV module information, click “Batch Delete”, and click “Confirm” to finish the operation.

文档更新时间: 2019-12-16 14:59   作者:admin