Create Plant
Clickon the homepage to enter the corresponding page by default.
Create Plan
A single plant can be created. Perform the following operations according to actual condition.
Viewing Basic Plant Information
Parameter name | Description |
---|---|
* Plant name | The name of a plant is the device serial number by default. |
*Plant type | Click to select the corresponding plant type. |
*Installed power (kWp) | Input installed power. |
*Country (Region) | Clickto select the country (region) of the plant. |
*Time zone | Clickto select the time zone where the plant is located. |
*Grid-connection type | |
Grid-connection date | Click to select the grid-connection date. |
Plant picture | Click to upload a plant picture. |
Note: * indicates required fields.
Plant location
Plant location, which can be added in two ways:
Manual entry: Manually enter the plant location in the input box;
Automatic access: Click on the map to automatically obtain the location and longitude and latitude information of the plant.
- Clickin the lower-right corner of the map or slide the mouse wheel up to zoom in the map.Click or slide the mouse wheel down to zoom out the map.
Parameter name | Description |
---|---|
*Plant address | Fill in the specific address of the plant |
Postcode | Fill in the postcode of the plant location |
*Longitude | Fill in the longitude of the plant location |
*Latitude | Fill in the latitude of the plant location |
Note: * indicates required fields.
Owner Information
Owner’s mobile phone: used to receive SMS
Configure Tariff (Optional)
Parameter name | Description |
---|---|
Unit | Clickto select the tariff unit. |
Feed-in tariff | The price of electricity sold to the grid. Enter tariffs in either of the following ways. 1.Enter feed-in tariff. 2.Turn on time-of-use tariff and fill in the feed-in tariff in different time segments. |
Consumption tariff | The price of electricity purchased from the grid. Enter tariffs in either of the following ways: 1.Enter grid tariff. 2.Turn on time-of-use tariff and fill in the grid tariff in different time segments. |
Add Communication Device (Optional)
Communication devices can be added in either of the following ways. - Manually add: Clickto select the device model, enter the S/N of the communication device, and click Add.
- Scan QR Code: Click Identify QR code to upload a picture of the device’s QR code or drag the image to the QR code identification box.
Click “Create Plant” below to finish adding.
Create Plants in Batch
Import plants in batches. Perform the following operations according to actual condition.
Plant Information
- Fill in the parameters and click Next to enter the batch import page.
Parameter name | Description |
---|---|
*Plant type | Residential |
*Country (Region) | Clickto select the country (region) of the plant. |
*Time zone | Clickto select the time zone where the plant is located |
Batch Import:
Click to download the template to local and enter the plant information according to the instruction in Excel and save it.
Click Batch Import and select the edited Excel file to upload.
Click Create Plant below to enter the overview page.
Overview
To view information about the plants that are being created.
Click Continue Batch Plant Creation to continue with the batch creation.
Click Complete. Create Plants in Batch finishes.